Plant Engineering > Pipeline Tools > Assign > Check ...
Use the Check functions to check the active pipeline or - in one step - all pipelines for invalid nominal diameter matings, or regarding the part structure.
Active pipelines |
All pipelines |
||
---|---|---|---|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
The part structure of a pipeline in 3-D Plant Engineering is subject to certain rules which must be respected to ensure an error-free execution of the processing functions.
You can use this function to check the structure of individual pipelines or all pipelines. The check can also be executed automatically after loading or before saving of a layout plan.
The active pipeline is examined to see if any parts with different nominal diameters have been joined. If any invalid nominal diameter matings are detected, the appropriate parts are marked.
This function is available for an individual pipeline as well as for all pipelines of the current drawing .
This marking is not removed until execution of the Redraw function. If an invalid nominal diameter mating is not detected, HiCAD issues an appropriate message.
When you insert a straight pipe in the drawing, it is internally noted whether this part only exists in a specified length or if it can be cut to fit. If it can, the valid maximum length is also recorded. Some functions, e.g. Move points, can change the length of pipe parts in the drawing.
When you select the Check pipe length function, the distance between connecting point 1 and connecting point 2 is detected, either for all pipe parts of a pipeline or all pipelines of the current drawing . If length values do not match, HiCAD differentiates between two cases:
In addition, an appropriate message is issued.
This function enables you to check whether the nominal diameters of parts belonging to the selected pipeline match the nominal diameter assigned to the pipeline. HiCAD highlights the parts that deviate from the given value. This marking is only removed after the Redraw function has been executed.
If no nominal diameter has been assigned to the pipeline, the check is not carried out and HiCAD issues an appropriate message..
Pipeline Tools (PE) • Plant Engineering Functions