When working with the Steel Engineering Drawing Management module you can choose between several procedures. It is your decision which one you prefer.
Here you will process, itemize and save all assemblies in one drawing. You create derived drawings, grant releases etc. in the original drawing. This procedure is described in Example 1.
![]() |
Unambiguous item numbers in the original drawing |
![]() |
Derived drawing(s) can only be created after completion of all assemblies. |
When working with very complex drawings, it can be useful to distribute the assemblies of the drawing among several workstations (Simultaneous/Concurrent Engineering.
Possibility 1: Completion of assemblies and drawing derivation in the detail drawings of the assemblies
Here you divide the original drawing into several suitable assemblies and save it, initially without itemizing the parts. Then, you save the assemblies of the drawing as externally referenced detail drawings. After this, processing, itemization and drawing derivation will not take place in the original drawing, but in the detail drawings of the assemblies. Due to the referencing, changes applied to the assemblies will, of course, also be applied to the original drawing. This procedure is described in Example 2.
![]() |
The assemblies can be processed at the same time on different workstations. After completion of an assembly, the corresponding drawings can be derived. |
![]() |
The item numbers in the original drawing may not be unambiguous. |
Possibility 2: Completion of assemblies in separate drawings, and drawing derivation in original drawing
Here you divide the drawing into several suitable assemblies and save them, without itemization, as externally referenced parts. Then, you assign these referenced assemblies to different workstations, where they will be completed by the respective, responsible person. After completion of all assemblies, the original drawing will be updated. After this, itemization and drawing derivation will take place in the original assembly (as in Example 1).
|
The processing of the assemblies can take place on different workstations. |
|
Derived drawing(s) can only be created in the original drawing after completion of all assemblies. |
|
The item numbers in the original drawing are unambiguous. |
![]() |